Structural Steel Mezzanine

Structural Steel Mezzanine for Offices in existing building.

This build involved organising workshop drawings for engineer approval. This required facilitating clear communication between all parties.

Once design approved, steel members were fabricated according to engineer’s design. This included fabrication of 125×5 SHS columns as well as 310UB40 & 360UB56 beams and painting in a zinc rich primer.
Steel was then delivered to site and installed to approved design. Installation included set out, installation of columns & beams, installation of purlins & Blue Tongue boards for flooring.

Project delivered on time and on budget. Client very happy with the final product